Essential road works – updated 14.05.19

Updated statement from SGN – 14.05.19

“Following recent stakeholder feedback, we have revised our programmes of works and will postpone the network upgrades required in Sun Lane, whilst the Open Gardens event takes place.

We will still need to start works in The Length on Monday 20 May, for everyone’s safety and to maintain traffic flow, we will need to have temporary traffic lights in place around our work area.

Our engineers will now begin working in Sun Lane from Monday 03 June for approximately three weeks.

We have completed our network upgrades in Sandalwood Drive, Manor Road and The Street.  

Our project is progressing extremely well and in consultation with Kent County Council we started upgrading our gas pipe in Bedford Way on Wednesday 24 April.

We appreciation your understanding and patience while we carry out essential gas mains replacement work in the area.

If you would like any further information, please call the I & G supervisor Tom Humphreys 07825 279122″

Paige Roberts – Stakeholder and Community Manager